Work out how much soil a dig produces — bank and loose cubic yards, weight in tons, and how many dump truck loads it will take to haul away.

Advertisement

Excavation Calculator

22.22 bank cubic yards
Bank volume600.00 cu ft (16.99 cu m)
Loose volume (after swell)27.78 cu yd
Estimated weight54,000 lb (27.00 tons)
Dump truck loads3 loads (10 cu yd each)

Bank volume is the soil in the ground; loose volume is what you haul after digging. Always call 811 (US) before you dig to mark buried utilities. Results are estimates.

Formulas:

Bank volume (cu ft) = Length (ft) × Width (ft) × Depth (ft)

Bank volume (cu yd) = Bank volume (cu ft) ÷ 27

Loose volume = Bank volume × (1 + swell factor)

Weight (lb) = Bank volume (cu ft) × soil density (lb per cu ft)

Truckloads = Loose volume (cu yd) ÷ truck capacity, rounded up

What Does an Excavation Calculator Do?

An excavation calculator works out how much soil comes out of a hole — for a basement, a foundation trench, a pond, a swimming pool, or a landscaping project — and what it will take to haul it away. You enter the length, width, and depth of the dig, the soil type, and the swell factor, and it gives you the bank volume (the soil still in the ground), the loose volume (the soil after digging, which is always bigger), the weight in pounds and tons, and the number of dump truck loads needed to remove it.

The number that surprises most people is the loose volume. Digging breaks soil apart and mixes air into it, so the pile that comes out of the hole is always larger than the hole it came from — typically 10 to 40 percent larger, depending on the soil. A hole of 20 bank cubic yards can easily produce 25 loose cubic yards, and it is the loose volume that fills the trucks. Estimating from the hole alone under-orders the haulage every time.

How to Use This Calculator

Measure the excavation in feet: length, width, and depth. For a trench, the length is the run of the trench and the width is the trench width. For an irregular shape such as a pond, split it into rectangles or use the average depth — a pond that is 4 feet deep in the middle and 1 foot at the edges has an average depth of about 2 to 2.5 feet, and estimating from the average is close enough for haulage planning.

Then choose the soil type and the swell factor. The swell factor defaults to 25 percent, which suits common earth and topsoil; the guide below gives typical factors for each soil type. Finally, enter the truck capacity — 10 cubic yards is standard for a single-axle dump truck, and 14 to 16 for a tandem-axle truck. The results update as you type, so you can try different depths and see how the truck count changes.

Bank Yards vs. Loose Yards: Why Soil Grows When You Dig It

Soil in the ground is compacted by its own weight over years or centuries. Digging breaks that compaction: clods separate, air gets between the particles, and the same mass of soil occupies more space. Excavators call the in-ground volume "bank cubic yards" and the dug volume "loose cubic yards", and the difference between them is the swell factor, expressed as a percentage.

Typical swell factors are: sand and gravel, 10 to 15 percent; common earth and topsoil, 20 to 25 percent; clay, 25 to 40 percent; and broken rock, 40 to 60 percent or more, because rock breaks into angular pieces that stack with large air gaps. Wet clay swells less than dry clay, because water already fills some of the pore space, but it weighs more — a tradeoff that matters for truck weight limits.

The swell factor also works in reverse when soil is put back. Soil that is backfilled and compacted returns to roughly its bank volume, or slightly more if it is not fully compacted — which is why a filled trench settles over the following year, and why backfill should be compacted in layers rather than dumped in all at once.

How Much Does Excavated Soil Weigh?

Soil weight depends on the type and the moisture content. This calculator uses these bank densities: topsoil 75 lb per cubic foot, common earth 90 lb, clay 100 lb, sand and gravel 110 lb, and broken rock 130 lb. In cubic yards, that is about 2,025 lb (just over 1 ton) per yard of topsoil, 2,430 lb (1.22 tons) of common earth, 2,700 lb (1.35 tons) of clay, 2,970 lb (1.49 tons) of sand and gravel, and 3,510 lb (1.76 tons) of broken rock.

Wet soil weighs significantly more than dry soil — saturated clay can reach 120 lb per cubic foot or more — so treat the weights as estimates for typical damp soil, and allow extra capacity if you are digging after heavy rain. Weight matters because trucks are limited by weight as well as volume: a truck rated for 10 cubic yards may only legally carry about 10 to 12 tons of payload, and 10 cubic yards of wet clay can weigh 15 tons, which means the truck has to run part-full. For heavy soils, the weight limit, not the volume, decides how many loads you need.

Worked Example

Say you are digging a rectangular pond 20 feet long, 10 feet wide, and 3 feet deep in common earth, with a 25 percent swell factor and a 10-cubic-yard truck. The bank volume is 20 times 10 times 3, which is 600 cubic feet, or 600 divided by 27 — 22.22 bank cubic yards. The loose volume is 22.22 times 1.25, or 27.78 cubic yards. The weight is 600 times 90 lb per cubic foot, or 54,000 lb — 27 tons. The truckloads are 27.78 divided by 10, rounded up: 3 loads.

Now a bigger job: a foundation excavation 30 feet by 20 feet, 4 feet deep, in sand and gravel with a 30 percent swell factor and a 12-yard truck. The bank volume is 30 times 20 times 4, or 2,400 cubic feet — 88.89 bank cubic yards. The loose volume is 88.89 times 1.30, or 115.56 cubic yards. The weight is 2,400 times 110, or 264,000 lb — 132 tons. The truckloads are 115.56 divided by 12, rounded up: 10 loads. At a typical haulage rate, those 10 loads are a significant part of the project cost, which is why an accurate estimate matters before the work starts.

Dump Trucks: How Much Does Each Load Carry?

A standard single-axle dump truck carries about 10 cubic yards and roughly 10 to 12 tons of payload. A tandem-axle truck carries 14 to 16 cubic yards and about 16 to 18 tons. A tri-axle truck carries 18 to 20 cubic yards, and a semi-trailer dump truck can carry 20 to 24 cubic yards — but larger trucks need more room to turn and may not be allowed on residential streets or small sites. The truck size you can use is often decided by access, not by preference.

For small jobs, a pickup truck bed holds about 2 cubic yards heaped, and a standard wheelbarrow holds about 2 cubic feet — moving 27.78 loose cubic yards by wheelbarrow would take about 375 trips, which is why even a small excavation is worth a truck or a skip. A 10-cubic-yard skip or roll-off container is the usual choice for a job too small for a dump truck but too big for a pickup.

Tips for Planning an Excavation

Call before you dig. In the US, call 811 at least a few days before any digging to have buried gas, electric, water, and telecom lines marked for free. Striking a gas line or a power cable is dangerous and expensive, and in most states it is a legal requirement to call first. Other countries have their own services — the principle is the same everywhere.

Plan where the spoil goes. The loose soil has to go somewhere, and a pile of 27 cubic yards covers a large area. If the soil stays on site, plan the spoil heap before digging starts, keep it away from the edge of the excavation (at least 2 feet back, and farther for deep digs), and remember that a heap of loose soil will spread and settle.

Allow for over-dig. Excavators rarely dig exactly to the line: a trench for a footing is usually dug a little wider than the footing, and the bottom is rarely perfectly level. Add 5 to 10 percent to the bank volume for over-dig on a machine-dug excavation, on top of the swell factor.

Common Mistakes to Avoid

The most common mistake is estimating haulage from the bank volume instead of the loose volume. A 22-bank-yard hole produces nearly 28 loose yards, and booking trucks for 22 yards leaves a third of the spoil still on site when the trucks leave. Always calculate the loose volume and book trucks against it.

The second mistake is forgetting the weight limit. A truck's volume rating and its weight rating are different limits, and for heavy soils the weight limit binds first. Check the payload rating with the haulage company and compare it with the tonnage this calculator gives you.

Finally, do not dig below the water table without a plan for the water. A hole that fills with groundwater needs pumping, the wet soil weighs more and is harder to handle, and the sides of a wet excavation are more likely to collapse. For any excavation deeper than 5 feet, US safety rules (OSHA) require protective systems — shoring, shielding, or sloping — and a competent person to inspect the dig daily.

Advertisement

Frequently Asked Questions

How many cubic yards are in a 20x10x3 foot hole?

22.22 bank cubic yards (20 x 10 x 3 = 600 cubic feet, and 600 / 27 = 22.22). After digging, with a 25% swell factor, the loose soil is 27.78 cubic yards — and it is the loose volume that fills the trucks.

What is the swell factor for excavated soil?

It depends on the soil: sand and gravel 10 to 15%, common earth and topsoil 20 to 25%, clay 25 to 40%, and broken rock 40 to 60% or more. Swell is the percentage the soil expands when dug, because air gets between the particles.

How much does a cubic yard of excavated soil weigh?

About 2,025 lb for topsoil, 2,430 lb for common earth, 2,700 lb for clay, 2,970 lb for sand and gravel, and 3,510 lb for broken rock. Wet soil weighs more — saturated clay can reach 120 lb per cubic foot.

How many dump truck loads is 27.78 cubic yards of soil?

3 loads in a 10-cubic-yard truck (27.78 / 10 = 2.78, rounded up). Always divide the loose volume, not the bank volume, by the truck capacity — and check the truck's weight limit too, since 27.78 yards of earth weighs about 27 tons.