Mortar & Plaster Calculator
Work out how much cement, sand, and water you need to plaster a wall or lay a brick wall — in bags, cubic feet, and gallons.
Mortar & Plaster Calculator
Assumes a 94 lb bag of cement = 1 cu ft, sand at 100 lb per cu ft, dry volume = wet volume x 1.33, and a 0.5 water-cement ratio by weight. Brickwork assumes standard bricks (8 x 2.25 x 3.75 in nominal) with 3/8 in joints. Results are estimates.
Formulas:
Plaster wet volume (cu ft) = Area (sq ft) × Thickness (in) ÷ 12
Brick mortar wet volume (cu ft) = Area × 6.86 bricks per sq ft × 14.44 cu in of mortar per brick ÷ 1,728
Dry volume = Wet volume × 1.33 (plus waste allowance)
Cement volume = Dry volume ÷ (1 + sand parts); Sand volume = Dry volume × sand parts ÷ (1 + sand parts)
Cement bags = Cement volume ÷ 1 cu ft per 94 lb bag, rounded up
What Does a Mortar and Plaster Calculator Do?
A mortar and plaster calculator works out how much cement, sand, and water you need for two common masonry jobs: plastering a wall (spreading a thin layer of cement mortar over brick or block to give a smooth finish) and laying a brick wall (the mortar that goes between the bricks). You enter the wall area, the mix ratio, and the plaster thickness or brick size, and it gives you the wet mortar volume, the dry material volumes, the number of cement bags, the sand in cubic feet and tons, and the approximate water needed.
Getting these numbers right matters because mortar is mixed fresh and used within about an hour or two — you cannot return unused mortar, and running out halfway through a wall leaves a visible joint where the new batch meets the old. Cement is also the expensive ingredient: a rich mix uses far more of it than a lean one, so choosing the right ratio saves real money on a large job.
How to Use This Calculator
Choose the job type first. For plastering, enter the wall area in square feet and the plaster thickness in inches — 1/2 inch is standard for a single-coat interior finish. For brickwork, enter the wall area only; the calculator works out the mortar from the standard brick size and joint thickness. Then pick a mix ratio and a waste allowance (10 percent is the default), and the results update immediately.
The headline result is the number of cement bags, because that is what you buy at the store. Below it are the volumes: wet mortar (what you will actually spread or lay), dry volume (the loose cement and sand before water is added), and the sand and water quantities.
Mix Ratios: What 1:4, 1:5, and 1:6 Mean
A mix ratio is written as cement to sand by volume. A 1:6 mix is one part cement to six parts sand — seven parts in total, of which one seventh is cement. A 1:4 mix is one part cement to four parts sand, or one fifth cement. The lower the second number, the richer the mix: more cement, more strength, more cost, and more shrinkage as it cures.
1:4 — rich mix. Used for exterior plaster exposed to rain, for wet areas such as bathrooms, and for pointing and repair work where strength and water resistance matter most. It is also used for the first coat of plaster on an exterior wall. The extra cement makes it stronger but more prone to cracking from shrinkage, so it is not used where a leaner mix will do.
1:5 — general purpose. A middle-ground mix for interior plaster and general brickwork where moderate strength is enough. It is a common choice for internal walls that will be painted or tiled.
1:6 — standard mix. The usual ratio for interior plaster and for most brick laying. It is strong enough for a single-story brick wall, economical on cement, and less prone to shrinkage cracking than richer mixes. Unless there is a specific reason to go richer, 1:6 is the default choice.
Why Dry Volume Is 1.33 Times Wet Volume
The most confusing step in mortar estimating is the dry volume factor. Wet mortar occupies less volume than the dry cement and sand it is made from, because the fine cement particles fill the air gaps between the sand grains, and the water fills the remaining voids. A cubic foot of dry cement plus six cubic feet of dry sand does not make seven cubic feet of wet mortar — it makes about five and a quarter.
The standard correction is to multiply the wet volume by 1.33 to get the dry volume. This is the factor used in quantity surveying textbooks and by estimators worldwide: dry volume equals wet volume times 1.33, which is roughly a 33 percent increase. The factor is not exact — it varies slightly with the sand's fineness and moisture content — but 1.33 is the accepted standard for estimating, and it is what this calculator uses.
Once the dry volume is known, the split between cement and sand follows from the ratio. For a 1:6 mix, cement is one seventh of the dry volume and sand is six sevenths. For a 1:4 mix, cement is one fifth and sand is four fifths. The calculator then converts the cement volume to bags: a standard US bag of Portland cement weighs 94 lb and occupies 1 cubic foot, so the number of bags is the cement volume in cubic feet, rounded up. Sand is converted to tons at 100 lb per cubic foot, the standard density for dry sand.
Worked Example: Plastering a Wall
Say you are plastering a wall 100 square feet in area, 1/2 inch thick, with a 1:4 mix and no waste allowance. The wet volume is 100 times 0.5 divided by 12, which is 4.17 cubic feet. The dry volume is 4.17 times 1.33, or 5.54 cubic feet. Cement is one fifth of that: 1.11 cubic feet, which is 1.11 bags — rounded up, 2 bags. Sand is four fifths: 4.43 cubic feet, or 0.22 tons. The cement weighs 1.11 times 94, or about 104 lb, and at a water-cement ratio of 0.5 by weight the water needed is about 52 lb, or 6.25 gallons (a gallon of water weighs 8.34 lb).
With a 1:6 mix instead, the same wall needs only 0.79 cubic feet of cement — 1 bag instead of 2 — and 4.75 cubic feet of sand. That is the practical difference the ratio makes: the richer mix nearly doubles the cement for the same wall, which is why 1:6 is the default unless the exposure demands richer mortar.
Worked Example: Brick Wall Mortar
For brickwork, the mortar volume comes from the geometry of the wall. A standard US brick is 7 5/8 inches long, 2 1/4 inches high, and 3 5/8 inches deep, and it is laid with 3/8-inch mortar joints. Including the joints, each brick occupies 8 inches by 2 5/8 inches of wall face, or 21 square inches — so a square foot of wall (144 square inches) holds 144 divided by 21, or about 6.86 bricks. Each brick needs a bed joint and a head joint totaling about 14.44 cubic inches of mortar, so each square foot of wall needs about 0.057 cubic feet of wet mortar.
For a 100-square-foot wall with a 1:6 mix and a 10 percent waste allowance, the wet volume is 100 times 0.057 times 1.10, or about 6.30 cubic feet. The dry volume is 6.30 times 1.33, or 8.39 cubic feet. Cement is one seventh: 1.20 cubic feet, or 2 bags. Sand is six sevenths: 7.19 cubic feet, or 0.36 tons. The wall needs 686 bricks — 100 times 6.86, rounded up. The water estimate is about 6.75 gallons.
Tips for Good Mortar
Measure by volume, consistently. Use the same bucket or gauge box for cement and sand every time, and level it off. Mix ratios are by volume, and an unmeasured shovel-load can vary by 30 percent or more, which changes the mix from batch to batch.
Mix dry first, then add water. Blend the cement and sand thoroughly before adding water, and add the water gradually. Mortar that is too wet is weak and shrinks badly; mortar that is too dry is hard to work and bonds poorly. The right consistency holds its shape on a trowel but spreads easily.
Keep plaster damp while it cures. Cement gains strength by reacting with water, and if plaster dries out too fast — in hot sun or wind — it stops curing and cracks. Mist the surface lightly for two to three days after plastering, and avoid plastering in direct sun or when the temperature is below about 40 degrees Fahrenheit.
Common Mistakes to Avoid
The most common mistake is forgetting the dry volume factor. Estimating cement and sand from the wet volume directly under-orders both by about a third, which is the single biggest cause of running short on a plastering job. Always multiply wet volume by 1.33 before splitting it into cement and sand.
The second mistake is measuring the wall area without subtracting doors and windows. A wall with a large window can have 15 to 20 percent less area than its overall dimensions suggest, and ordering for the gross area wastes cement and sand.
Finally, do not use beach sand or sand with salt or clay in it. Salt causes efflorescence — white stains that bloom on the finished surface — and clay weakens the mortar and causes cracking. Use clean, washed plastering or masonry sand from a builders' merchant.
Frequently Asked Questions
How many bags of cement do I need to plaster 100 sq ft at half an inch thick?
2 bags with a 1:4 mix, or 1 bag with a 1:6 mix. The wet volume is 4.17 cubic feet, the dry volume is 5.54 cubic feet, and the cement share depends on the ratio — 1.11 cubic feet at 1:4, 0.79 cubic feet at 1:6.
What is the best mix ratio for plaster?
1:6 (one part cement to six parts sand) is standard for interior plaster, and 1:4 is used for exterior or wet-area plaster where extra strength and water resistance matter. Richer mixes cost more and shrink more as they cure.
Why is dry volume 1.33 times the wet volume?
Because cement particles fill the air gaps between sand grains and water fills the remaining voids, so wet mortar occupies about a quarter less volume than its dry ingredients. Multiplying wet volume by 1.33 is the standard estimating correction.
How many bricks are in a 100 sq ft wall?
About 686 standard bricks, at 6.86 bricks per square foot including 3/8-inch mortar joints. That wall needs about 6.3 cubic feet of wet mortar with a 10% waste allowance, or 2 bags of cement at a 1:6 mix.
How much water does mortar need?
About half the weight of the cement, a water-cement ratio of 0.5. For a 100 sq ft plastered wall at 1:4, that is about 6.25 gallons. Add water gradually — mortar that is too wet loses strength and cracks as it dries.